Renovation Project Report - Day 40

Friday Afternoon.  Here are some photos of this week. 

Carpet being installed
Henry hard at work.

Bill, Roger & Henry stripping the wax off the floor

The shiny floor!

Sawatzky's checking out the wall! 

We're almost ready to move upstairs on Sunday.
The sound needs to be installed, but that will have to wait.  Our current sound system still works! 
Saturday at 11:00 am.: 
Pews need to get moved back in.
Windows wiped off once more.
Dusting in the rest of the church. 

Then, we'll walk up together on Sunday morning and celebrate!



Ruth

Friday, November 5, 2010

Renovation Project - Day 33

Good morning,
Things are happening in the sanctuary! 
1.  The front of the sanctuary walls just need one more coat of paint.

Tuesday  morning

Tina checking out the back wall painting

The box to cover up the stairwell made into a storage unit. 

Friday morning and getting all polished up.


2.  The electricians installed the track lighting. 
Wednesday - note the walls


Movable track lighting

Ready for switches

3.  Plumbers installing the heating units.



4.  Looking ahead.
Friday evening - moving pews out of the sanctuary, putting up second scaffolding
Saturday morning -9:00 cleaning of the ceiling - the biggest and dirtiest job!
BYO Bucket and old towels.
Next week:  carpet to be installed, soldering of electrical parts, floor to be stripped and waxed.
Move back in - all the pews, books, put organ and piano into place etc. 
Walk up service next Sunday November 14.
Dedication service Sunday November 21 at 4:00 pm.