Renovation Project Report - Day 40

Friday Afternoon.  Here are some photos of this week. 

Carpet being installed
Henry hard at work.

Bill, Roger & Henry stripping the wax off the floor

The shiny floor!

Sawatzky's checking out the wall! 

We're almost ready to move upstairs on Sunday.
The sound needs to be installed, but that will have to wait.  Our current sound system still works! 
Saturday at 11:00 am.: 
Pews need to get moved back in.
Windows wiped off once more.
Dusting in the rest of the church. 

Then, we'll walk up together on Sunday morning and celebrate!



Ruth

Friday, November 5, 2010

Renovation Project - Day 33

Good morning,
Things are happening in the sanctuary! 
1.  The front of the sanctuary walls just need one more coat of paint.

Tuesday  morning

Tina checking out the back wall painting

The box to cover up the stairwell made into a storage unit. 

Friday morning and getting all polished up.


2.  The electricians installed the track lighting. 
Wednesday - note the walls


Movable track lighting

Ready for switches

3.  Plumbers installing the heating units.



4.  Looking ahead.
Friday evening - moving pews out of the sanctuary, putting up second scaffolding
Saturday morning -9:00 cleaning of the ceiling - the biggest and dirtiest job!
BYO Bucket and old towels.
Next week:  carpet to be installed, soldering of electrical parts, floor to be stripped and waxed.
Move back in - all the pews, books, put organ and piano into place etc. 
Walk up service next Sunday November 14.
Dedication service Sunday November 21 at 4:00 pm.

Friday, October 29, 2010

Siding and Stone samples

Jake & Donna have collected a number of sampels of siding and stone for our consideration. 

Stone

siding which looks like stone

siding

stone - same type of material as on the inside

stone - same type of material as on the inside

stone - comes individually so it would have mortar lines

stone - it comes in sections like this

stone - with individual stones, so it would have mortar lines

Please take a look at these and come prepared to talk about this on Sunday.  Financial details will be presented at the congregational meeting. 

Jake

Renovation Project Day 26 Report

This morning everything is quiet and in waiting. 


The brick work is complete. 




The work on the trim for the windows is underway. 



In order to hide the stairwell and to blend things in a hanging file drawer
for the pianist and organist music is being created. 

Staining and painting estimated to begin on Monday, but we'll see where things are at by the end of today. 


Ruth

Wednesday, October 20, 2010

Renovation Project - Outside Material Information

On Sunday, October 17 after the church service, we had a congregational meeting where its was decided that information and pictures of the possible choices for outdoor materials regarding the renovation would be posted here.

Then we will have another congregational meeting on October 31 to discuss and decide on these options.



Ready for new siding/brick

Option 1 - Reside the church to match what we had before.
    Here are pictures of the siding that we have on other areas of the church.


Foyer peak area

Ditto








Foyer entrance - both door areas

Above the front entrance








Back foyer area

west sanctuary windows









east sanctuary windows

Here is a "rough look" with the same siding that we had:




Pros: Least expensive, match other sided areas
Cons: "Ugly"

Option # 2 - Stone


closeup look


medium look








faraway look





look with contrasting brick


Here is a "rough look" with stone:


Please note, that further options will be posted here, once I receive them from the renovation committee.
So come back often to see if there are any updates.


Allen




Renovation Project - Day 16 Report

Hi:

Here are a couple pics.


No changes since Friday

Rock to be used on the wall.




Allen




Friday, October 15, 2010

Renovation Project - Day 12 Report

At three o'clock the stage is all closed in.

Wednesday evening - October 13

Outside - October 13, 2010

Drywall is almost done

Stage corners


The dry wall is up at the front at the sides.

The cross area is ready for ledge rock.

All is cleaned up.


Donna was here to check on the progress and left with a "to do" list.

Jake is busy checking out cost details and getting ready for the meeting on Sunday.

Charlotte has been taking photos and spent all day at the office.



Stairwell wall soon to be clad in oak

Clean and ready for Monday

We will have a meeting on Sunday after church for more updates and a possible decision about finishing the outside exterior wall. 



Charlotte & Ruth